Owner: New York City Department of Environmental Protection

Client: Schiavone Construction Co. and WDF Corp, A Joint Venture

Location: Brooklyn, New York

Construction Cost: $ 394 Million

The New Central Residuals Building is a key element of the transformation of New York City’s largest wastewater plant into one of the nation’s largest state-of-the-art treatment facilities. The approximately 70,000-square foot steel and concrete structure will house fine secondary wastewater screens, sludge screens, grit-washing equipment, skimming concentration equipment and containers to collect all plant residuals for removal by truck.

Service Provided:

  • Pre-Construction Building Condition Survey
  • Preparation of Instrumentation and Monitoring Plan for Existing Structures
  • Preparation of Vibration Monitoring Plan
  • 12 months of Vibration Monitoring during Pile Driving

Newtown Creek 3Newtown Creek 2